Hershey's Sweet Victory - ' What Went Wrong ' (
Page 2 of 5 )
#1: The Big Bang">
What Went Wrong #1: The Big Bang
The overriding problem appears clear: Hershey was simply trying to do too
much at once. In cosmology, the Big Bang theory tells us the universe sprang
into being in an instant, wiping out everything that went before. In Hershey's
case, it was the old logistics systems that had allowed it to do business for
years that were wiped out in a flash.
In late 1996, Hershey's management approved what came to be known as the
Enterprise 21 project, which would largely replace legacy mainframe systems with
new enterprise client/server software. Enterprise 21 was partly a Year 2000
project, allowing Hershey to scrap rather than repair legacy software that might
not process date-related procedures correctly after the turn of the century. But
the new systems were also supposed to allow Hershey to change and streamline its
business processes.
Hershey selected SAP to provide the heart of the system, which would be
complemented by planning and transportation management software from
Manugistics, and new sales software from Siebel Systems. Siebel doesn't seem to
have had much to do with what went wrong, though by including it Hershey put a
third major systems implementation project on its plate.
Hershey wasn't inexperienced with Manugistics, having used mainframe versions
of its software for years, but now it was switching to a client/server version
that would be configured as a bolt-on to SAP. Much of the project's complexity
was in the integration of the SAP and Manugistics software, which had to work
together to manage orders and schedule shipments to customers.
Indeed, Alan Stenger, a professor at Penn State's Center for Supply Chain
Research who has studied the 1999 mishap, says some Hershey executives wanted to
supplement principal integrator IBM Global Services with another consulting firm
that had more experience with the SAP-Manugistics interface. Hershey's
management chose not to take that step.
Although the plan had been to switch on the new systems in Aprilan off-peak
time for candy orders the project ran behind schedule and wasn't completed
until July. With Halloween orders already starting to roll in and the immovable
Y2K deadline looming, Hershey decided in favor of a direct cut-over strategy in
which all the new software would be turned on at once; it rejected another
strategy in which the system would have been phased in one module at a time. The
problems caused by this abrupt transition weren't immediately apparent, but
essentially orders began falling through the cracks. Despite having plenty of
inventory on hand, Hershey couldn't get it to customers.
By September 1999, in any event, it was too late for Hershey to backpedal. It
had essentially demolished its old logistics systems to make way for the new
one, and workers spent the next few months going through contortions to work
around the problems and ship candy despite the system, rather than through it.
Lesson Learned: Go Slowly
To be fair, in 1999 Hershey was rushing to meet an immovable deadline, since
it was trying to get off legacy systems that might not continue to work
correctly as of Jan. 1, 2000. Still, Hershey has demonstrated success in the
years since with a less-hurried, methodical approach that leaves time for
testing.
After stabilizing SAP and the attendant systems, Hershey found itself with
something that was merely acceptable. So after a careful redesign, it began work
on the upgrade to mySAP in July 2001. The work was completed in 11 months, 20%
under budget, and without disruption to customers, according to Hershey and its
partners. With this release, Hershey says it has consolidated the processing of
more than 95% of its revenue and business transactions within a single system.
Hershey is also using SAP's Business Warehouse for analytic applications for
marketing and brand managers. Besides upgrading to the latest SAP software,
Hershey said it was able to enhance business processes central to its order
management, such as generation of the "pick lists" used by warehouse workers to
pull together all the products that make up a shipment to a particular customer.
There's another Hershey project that shows how its approach to big projects
has changed. The opening in 2000 of a new Eastern distribution center, EDC III,
was part of an initiative to strengthen the overloaded physical logistics
infrastructure that exacerbated the systems problems of 1999, but it also had a
systems component. For the first time, Hershey was dictating the choice of
warehouse management software, a decision that previously had been left at the
option of the third-party logistics companies it hired to manage its warehouses.
Hershey picked a solution from RedPrairie (then known as McHugh Software).
Speaking at RedPrairie's user conference earlier this year, Kenneth D.
Miesemer, director of Eastern distribution operations at Hershey, made the
connection explicit. "Hershey had really come out of a bad ERP system
implementation, so this project was very critical," he said.
This time, Hershey made sure to take the time and resources to thoroughly
test the computer systems. Testing included putting bar codes on empty pallets
and going through the motions of loading them onto trucks so that any kinks
would be worked out before the distribution center opened for business. "If we
had any problems, we wanted to keep it out of the press," Miesemer said.