Cool Cash - ' The Big Chill ' (
Page 2 of 3 )
The Big Chill
The planning process began in 2003, when Culver and his team
worked with contractors, architects and consultants to design
the facilities. Wells Fargo hadn't had excessively high energy
costs in its other data centers, but with the new construction,
Culver saw an opportunity to explore measures to lower consumption.
That's become standard operating procedure for
builders, so he and his team decided to run with it.
In the Minneapolis facility, Culver had to decide which
kind of economizer to use. (Economizers are mechanical
devices that help regulate energy usage.) One option was an
air-side economizer, which uses air from outside the facility to
cool the environment inside. But there was a downside: That
would mess with the humidification needed to keep the air
from becoming too dry, Culver says.
Instead, Culver turned to water-side economizers, which
use evaporating water from a water tower to counteract heat
emitted from servers. This method, known as "free cooling,"
let the company forgo chillers—machines that cool the water
used to dehumidify the facility. That saved the company 300
kilowatts an hour per chiller, or about $150,000 a year so far,
which Culver expects to double in the next two years.
The firm also looked into floor-level cooling for the
Minneapolis data center. Many data centers use self-sustaining
air conditioning units scattered around the floor and linked
to chillers to distribute cool water. But Wells Fargo had eliminated
the chillers, and for the density of servers in the facility,
Culver and his team decided to go a different direction.
The engineering firm Wells Fargo had contracted for this
project had built a central fan system for American Express,
which had a lower-density data center. So Wells Fargo had
the firm adapt that system to its new facility. The system is
computer controlled and lets
facility managers monitor how
powerfully the fans operate at
any given time. "It allows us
to put the air where we need
it," Culver says. "The system
only works as hard as it needs
to because it's regulated by the
computer system."
And, he adds, it saved the
company about 15 percent in
power consumption.
In Tempe, though, Culver
and his colleagues had to cope
with an entirely different climate.
Without Minneapolis'
constant cooler temperatures,
the Tempe facility wasn't a candidate
for free cooling. So here
the company used the modified
floor-cooling system with variable-
speed fans and chillers.
The controls in place at the two facilities have yielded
impressive performance results: Both data centers have had 100
percent uptime since they went into operation, Culver says.