The Layton Companies: Paper Chaste - ' Playing Catch' (
Page 2 of 3 )
-Up">
Playing Catch-Up
For Layton, this was the legacy of an application called Construction Industry
Software (COINS) developed by Shaker Computer and Management Services Inc. in
Latham, N.Y.
Coins "was what was here when I got here and we were at least a version or two
behind the most recent version," says Layton chief information officer Steve
Wright. "It was a very old system and it wasn't keeping pace with our growth."
The Layton Companies' combined sales surged 33% from $270.3 million in 1999
to $358.7 million in 2002. It estimates sales climbed 10% to 15% for the year
ended Dec. 31, 2003, and that they'll increase by the same percentage again
this year.
For the four companies under Layton's umbrella, more than 150 different projects
can be ongoing at any one time. When on-the-fly changes to the general-contracting
plan were made by a given customer, each change and billing order had to wend
its way through the old, sluggish system, usually resulting in cost overruns
and further delays.
The company's margins were decreasing because projects scheduled to be completed
in five weeks were actually taking six or seven. Contractors originally supposed
to be on site for only two days were working four or fiveall at Layton's
expense. As a privately held company, Rindlisbacher declined to specify how
much margins have decreased, saying only that it was "significant." "Our volume
kept jumping but our margins were shrinking," he says. "The technology was a
big part of the problem."
Under the old billing system, accountants and corporate officers could not easily
obtain necessary data or documents. "We needed a way to empower our men out
in the field so they could have access to the information immediately and get
the costing and approvals they needed in minutes or hours rather than days and
weeks," Wright says.
In May 2001, Wright and his three-person information-technology team finally
decided to abandon their old-fashioned paper chase and try enterprise- and project-management
software designed for the construction industry by Computer Methods International
Corp. (CMIC). Seven months later, Layton had integrated the core financials,
project-accounting, subcontracting and payroll applications with its existing
R/S 6000 platform and Oracle database.
The new system, which cost $750,000, gives Layton executives a real-time snapshot
of the entire financial history and status of all current projects. Project
managers and accountants now have the ability to approve billing orders from
laptop or desktop computers instantly, and have access to detailed information
about materials and labor costs.
Each project is tracked online and gives accountants, executives and on-site
workers an opportunity to share and extract data such as the amount of concrete
needed for each phase of the foundation or steel to be used for the interior
walls. Meanwhile, the consolidation of all this data means that a project manager
working a similar project in another part of the country can see how his colleague
priced a particular portion of a job.
"We can't really quantify how much this one function has saved us but there's
no question we're now more accurate and on target when it comes time to bid
[on] a joband that's where the money is made," Rindlisbacher says.
"In our business, it's all about the bid. Once you've got the job, it's your
responsibility to finish the job to specifications. If you didn't bid it properly,
that's your tough luck."
With scores of jobs going at any one time and each job spanning from a few months
to several years, the cost-transaction and accounts-receivable functions can
now be identified and monitored for a given time period. Being able to purchase
concrete in large quantities for multiple projects rather than buying a little
at a time for each individual structure is just one of the advantages Layton
now enjoys.
Also, Rindlisbacher can see on a minute-to-minute basis how much is being spent
and how much will be earned from a multi-year project such as the new airport
in Boise, Idaho. He and other Layton managers can quickly pull up the overall
running cost of the airport project, broken down by each of the 20-plus subcontractors
working the project.
When executives see, for example, that the plumbing contractor installing the
bathrooms for the terminal is closing in on either the total cost or time allocated
to that portion of the job, they can have the on-site project manager investigate.
If it's running behind schedule, Layton managers will make sure the plumbing
contractor picks up the pace or else they'll move up other projects, perhaps
the lighting systems, to ensure the overall project doesn't fall too far behind
schedule.
"It gives us the chance to focus on and monitor our subcontractors much closer
than before," Wright says.
Moreover, any employee with proper clearance can see exactly how many subcontracts
are outstanding on a projecthow many nails, screws, cubic feet of sheet
metal are and will be used and how that compares to a similar job going on 2,000
miles away. Instead of sending an entire supervisory teamproject manager,
accountant, etc.to job sites throughout the U.S., Layton can now monitor
projects remotely, saving travel costs while improving communication at each
job site.
"It's changed the way we do everything," Wright says. "We can now have a project
manager effectively run a site in Las Vegas from right here in our corporate
offices in Sandy. It's a lot easier to have everyone in the same room here rather
than some in Tennessee and some in Arizona and everyone trying to communicate
through handwritten notes and cellular-phone calls."
With a clearer picture of where each individual job stands, The Layton Companies
can better project its annual results and budgets and deliver more-accurate
bids faster than competitors who still rely on the labor-intensive practice
of hunting and pecking through years of paper references.
A 115,000-square-foot office building requires the same amount of steel, concrete,
tile, paint and other materials in Massachusetts as it does in Colorado. After
completing one job, all the pertinent dataincluding the contractors used,
time allotted for each segment and total cost of each stageare logged
and stored online in the new system.
When another office building of similar size is up for bid, Layton Companies
can now pull up this historic data with a few keystrokes and know exactly how
much time and money will be needed to complete the building. Better yet, the
system also shows where and why cost overruns or savings developed and that
information is then factored into the bidding process.
"If we cut our estimate too close on the last office building and we can now
see exactly where and why that happened, we can adjust our bid for the next
job and make sure that those overruns are avoided," Rindlisbacher says. "With
the old system, we just knew we didn't make enough money and heard a lot of
clutter about how and why from different contractors. Now we have the line-item
and dated data to recreate an entire job."
"In essence, budgeting and forecasting are non-value-added processes," says
Eric Austvold, an analyst at AMR Research. "It's a point-in-time guess at what
a company wants a year later. You want a system that helps you manage the data
so that you can make better assumptions."
Equally important, Wright says, is finding a vendor partner who understands
your business as well as you do.
Toronto-based CMIC came out of the mid-1970s as a customer-software firm focusing
on the intricacies of the construction industry. Unlike most industries, construction
calls for very unusual data fields that typically aren't satisfied by off-the-shelf
enterprise-resource-planning or customer-relationship-management software packages
from large vendors.
For example, the concept of "retainage" accounting applies to virtually every
construction project. In essence, this form of accounting means that subcontractors
aren't paid until the job is 100% completed. Otherwise, a subcontractor can
put a lien on the project and prevent future work from being completed.
Because contractors are billing the costs of the project and then adding a fee,
it's not possible for most generic enterprise-software systems to make that
distinction in real-time.
"We've learned how to anticipate just about everything that a mid- to large-sized
general-contracting company would run across," says Gord Rawlins, president
of CMIC. "This product we're selling now CMIC Project Management software has
only been around for about 10 years but it comes with almost 30 years of real-life
experience behind it," he says, referring to the product, which has evolved
since the mid-1970s.
And Layton has learned that now it can use fewer project managers to manage
multiple sitessometimes remotelyand reduce its accounting staff
by 25% while taking on more projects in shorter periods of time. "We're getting
more bids now because we're able to cut it much closer with much more confidence
than we ever had before," Rindlisbacher says. "That's real ROI."